South Side Lift Station Replacement

Scope of the lift station replacement included design, construction plans and specifications, product research, DEQ report and completion of the bidding process.

Construction consisted of replacement of the wet well and submersible pump system, removal of the existing pumps, electrical, sensors and guiderails; installation of a package lift station, pumps, guiderails, sensors,  electrical utilities and telemetry.  Installation of a riser/bypass on the existing 4” force main downstream of the wet well to utilize temporary pumping to bypass the existing lift station during project construction.

Before

Before

After

After